Environmental equipment | home of craftsmen
Professional supplier and service provider of thermal equipment
Horizontal (condensing) oil (gas) steam boiler in the new installation, or recently remodeled boiler energy efficiency testing needs to be carried out to ensure the normal use of the boiler, to protect the effectiveness of the boiler. So in Dongguan, horizontal (condensing) oil (gas) steam boiler energy efficiency test how to handle, where to handle?
I am here to introduce horizontal (condensing) oil (gas) steam boiler energy efficiency testing guidelines.
First, the scope of acceptance
1, newly installed boilers; 2, the recent renovation of the boiler; 3, in-use boilers.
Second, the conditions
1, for the newly installed boiler energy efficiency testing, the following information (remodeling or in-use boilers are not required):
(1) boiler design specifications (including the design of the power range, design fuel requirements and fuel belongs to the classification); (2) boiler general drawing;
(3) boiler thermal calculations (including boiler design load range calculated thermal efficiency curve);
(4) boiler flue gas resistance calculations;
(5) boiler water resistance calculation;
(6) Boiler instruction manual;
(7) The use of oil, gas burner type.
2, remodeling or in-use boilers need to provide:
(1) boiler license;
(2) Boiler product quality certificate;
(3) remodeling thermal calculations (if any).
3, the tested boiler, auxiliary systems should meet the following conditions:
(1) the boiler can be in the design output, parameters allow safe and stable operation;
(2) Auxiliary systems should be matched with the boiler output, normal operation (there should be no running, bubbling, dripping, leaking);
(3) The fuel used in the test should meet the requirements of the designed coal;
(4) The boiler and auxiliary systems should be able to meet the test outline of the test point layout requirements
4, the boiler under test before the test should achieve thermal stability, that is, the boiler's main thermal parameters fluctuate within the range of no more than 5%, and the average value does not change over time. The time required for thermal stability is:
(1) Not less than 2h for oil and gas boilers of pot-shell type without brick wall (fast and assembled) and not less than 4h for coal-fired boilers;
(2) For light furnace wall boilers not less than 8h;
(3) for heavy furnace wall boilers not less than 24h.
Third, the procedure
(1) appointment test acceptance
Boiler using units to the Guangdong Provincial Special Equipment Testing Institute, Dongguan Branch of the business window or chemical supervision and inspection room business window to receive "industrial boiler energy efficiency testing commissioned acceptance form.
(2) acceptance procedures
① boiler using units (or installation companies) with the relevant person in charge of the "industrial boiler energy efficiency test commissioned acceptance of the single" to the chemical supervision and inspection room and energy efficiency testing responsible for the signing of the acceptance of the single, and then go to the business window of the hospital for payment procedures.
② to be put into production units, boiler normal operation, boiler units (or installation company) notify the chemical supervision and inspection room of my hospital to make an appointment to test the energy efficiency of the relevant personnel.
(3) Confirmation of on-site testing conditions
Before the test, the test-related personnel to the boiler using units to view the operating conditions of the boiler, and make preparations for the test, if necessary, to prepare the test outline.
IV. Payment
(1) The test applicant holds a UnionPay card and pays the fee by swiping the card at the fee window of our branch;
(2) Transfer the money (see the acceptance form for details of the transfer account).
V. Report Collection
After the completion of the test work, after fifteen working days with the "Industrial Boiler Energy Efficiency Test Commission Acceptance Slip" to the Chemical Supervision and Inspection Laboratory of the Institute to receive the report at the window of the report issuance.
Sixth, contact us
Website: http://www.dgee.dg.gov.cn E-Mail:dgtjsz@163.com
Boiler media testing office telephone: 0769-23061896/23061870/23061895 (fax)
Zip Code: 523416
Chemical Supervision and Inspection Laboratory Address: Liaobu Town, Dongguan City, Guangdong Province, Xiangyuan East Road, the middle of Tuen Village
Contact Us
National service hotline:13829262146
Address:No. 6, Road 1, Shegang Industrial Zone, Humen Town, Dongguan, China
TEL:0769-85245101
fax:0769-85247528
Email:13829262146@139.com
technical support:MYIT
Scan QR code to share to WeChat
0769-85245101